NO.1 Your organization uses Microsoft Project 2013. You are finalizing the Project Schedule for a
very complex project with over 100 resources. You need to ensure that all tasks are assigned to
resources. What should you do?
A. Use Resource Graph view and look for the Unassigned resource name.
B. Use Task Usage view and look for Unassigned tasks.
C. Use Resource Usage view and look for the Unassigned resource name.
D. Use Resource Sheet view and look for Unassigned tasks.
Answer: C

74-343 技術   

NO.2 You are project manager who uses Project Professional 2013. Your organization uses Microsoft
SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project.
The task list contains over 100 items. You need to create a project based on the tasks in the
SharePoint list in the most efficient manner. What should you do?
A. Export the tasks into Microsoft Excel and then import the Excel file into Project Professional 2013.
B. Edit the Project Summary Task hyperlink column to point to the SharePoint task list and click the
Import button.
C. Copy and paste the tasks from SharePoint into Project Professional 2013.
D. Open the tasks directly from the SharePoint site into Project Professional 2013.
Answer: D

74-343 関連   

NO.3 You are managing a project using Project Professional 2013.
Your project schedule is showing task overallocation indicators in the Gantt chart view.
You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details
for BA1 to understand their current workload before making any assignment changes. What should
you do?
A. Right-click the BA1 resource and select Information.
B. Click the BA1 resource and scroll to the end of the project.
C. Click View, check Details, select Resource Form then click on the BA1 resource.
D. Click View, check Details, select Task Form then click on the BA1 resource.
Answer: C

NO.4 You are a project manager who uses Project Standard 2013.
You are creating a preliminary project schedule and are estimating the number of resources
required prior to finalizing the schedule.
You do not have named resources to complete the tasks, but you know the resource roles that are
necessary. One of the roles needed is architect.
You need to estimate how many architect hours are required to complete the work. What should
you do?
A. Add a Material Resource named architect.
B. Add a Budget Resource named architect.
C. Add a Work Resource named architect,
D. Add a Cost Resource named architect.
Answer: C

74-343 ファンデーション   

ショートカットを選択し、テクニックを使用するのはより良く成功できるからです。98-366 試験準備に一発合格できる保障を得たいなら、JapanCert の98-366 試験準備はあなたにとってユニークな、しかも最良の選択です。これは賞賛の声を禁じえない参考書です。この問題集より優秀な試験参考書を見つけることができません。この98-366 試験準備では、あなたが試験の出題範囲をより正確に理解することができ、よりよく試験に関連する知識を習得することができます。そして、もし試験の準備をするが足りないとしたら、98-366 試験準備に出る問題と回答を全部覚えたらいいです。この問題集には実際の98-366 試験準備のすべてが含まれていますから、それだけでも試験に受かることができます。

自分のIT業界での発展を希望したら、Microsoftの74-343 模擬モードに合格する必要があります。Microsoftの74-343 模擬モードはいくつ難しくても文句を言わないで、我々JapanCertの提供する資料を通して、あなたはMicrosoftの74-343 模擬モードに合格することができます。Microsoft74-343 模擬モードを準備しているあなたに試験に合格させるために、我々JapanCertは模擬試験ソフトを更新し続けています。

購入した前にMicrosoftの98-366 試験準備のような商品の適用性をあなたに感じさせるために、我々はMicrosoftの98-366 試験準備のデモを提供して、あなたはJapanCertで無料でダウンロードして体験できます。何か疑問があれば、我々の係員を問い合わせたり、メールで我々を連絡したりすることができます。あなたは弊社を選ぶとき、Microsoftの98-366 試験準備に合格する最高の方法を選びます。

98-366試験番号:98-366 試験準備
試験科目:「MTA Networking Fundamentals」
最近更新時間:2017-02-15
問題と解答:176

>> 98-366 試験準備

 
74-343試験番号:74-343 模擬モード
試験科目:「Managing Projects with Microsoft Project 2013」
最近更新時間:2017-02-15
問題と解答:101

>> 74-343 模擬モード

 

人々は異なる目標がありますが、我々はあなたにMicrosoftの98-366 試験準備に合格させるという同じ目標があります。この目標を達成するのは、あなたにとってIT分野での第一歩だけですが、我々のMicrosoftの98-366 試験準備を開発するすべての意義です。だから、我々は尽力して我々の問題集を多くしてJapanCertの専門かたちに研究させてあなたの合格する可能性を増大します。あなたの利用するMicrosoftの98-366 試験準備が最新版のを保証するために、一年間の無料更新を提供します。

購入前にお試し,私たちの試験の質問と回答のいずれかの無料サンプルをダウンロード:http://www.japancert.com/74-343.html